Step-by-step
installation.
How to mount ARP hardware accurately on site. Contact us anytime if you have questions about substrates, post spacing, or anchors.
- [1]Horizontal mounting shoe MH
- [2]Concrete screws
- [3]3× M6 levelling screws
- [4]Circular spirit level (for alignment)
- [5]Post screws
- [6]Handrail bracket (HT / HTI)
- MH= Horizontal mounting shoe (top-mounted)
- 40= Post profile (40 = 40/40 · 60 = 60/40 mm)
- 240= Shoe length (240 mm · also 190 / 300 / 440 mm)
- Posts
- 40/40 mm or 60/40 mm
- Lengths
- 190 – 440 mm
- Levelling
- 3 M6 levelling screws
- Anchoring
- Concrete screws + injection mortar
Horizontal mounting shoes
- 01
Drill the anchor holes at the desired position and spacing.
- 02
Clean the drill holes and mounting surface thoroughly to remove dust.
- 03
Turn the 3 M6 levelling screws [3] into the mounting shoe [1] until they protrude approx. 3–4 mm underneath.
- 04
Position the mounting shoe [1] and loosely fit the concrete screws [2] as a counterhold.
- 05
Dry-level the mounting shoe [1] precisely using the 3 levelling screws [3] and the circular spirit level [4].
- 06
Press injection mortar through the injection holes underneath the shoe [1], allow to cure, and then tighten the concrete screws [2] firmly.
- 07
Screw in the upper post screw [5] on the balcony post and slide the post onto the mounting shoe [1].
- 08
Mark the desired height using a laser or chalk line, remove the post, and cut it squarely at 90°.
- 09
Place the post back on, insert the lower post screw [5], plumb with a spirit level, and tighten firmly.
- 10
Insert the required handrail bracket [6] into the top of the balcony post.
- [1]Vertical mounting shoe MV
- [2]3× M6 levelling screws
- [3]Concrete screw
- [4]Post screws
- [5]Handrail bracket (HT / HTI)
- MV= Vertical mounting shoe (fascia mounting)
- 40= Post profile (40 = 40/40 · 60 = 60/40 mm)
- 130= Plate height (130 mm · also 100 mm)
- 40= Projection (40 / 80 mm · H = timber beams)
- Posts
- 40/40 mm or 60/40 mm
- Cantilever
- 25 / 40 / 80 mm
- Timber mount
- MV40-H and MV60-H
- Benefit
- 100% usable balcony floor space
Vertical mounting shoes
- 01
Drill the anchor hole at the desired position and spacing along the slab edge.
- 02
Clean the drill hole and fascia surface thoroughly to remove dust.
- 03
Turn in the 3 M6 levelling screws [2] until they protrude approx. 3–4 mm on the back.
- 04
Position the mounting shoe [1] and loosely insert the concrete screw [3].
- 05
Dry-level the mounting shoe [1] precisely using the 3 levelling screws [2] and a spirit level.
- 06
Press injection mortar through the injection holes behind the shoe [1], allow to cure, and then tighten the concrete screw [3] firmly.
- 07
Screw in the upper post screw [4] on the balcony post and slide the post onto the mounting shoe [1].
- 08
Mark the desired height using a laser or line, remove the post, and cut it squarely at 90°.
- 09
Place the post back on, insert the lower post screw [4], plumb with a spirit level, and tighten firmly.
- 10
Insert the required handrail bracket [5] into the top of the balcony post.
- [1]Fence mounting shoe MZ
- [2]Concrete screw
- [3]Post screws (upper & lower)
- [4]Weather-resistant post end cap
- MZ= Fence mounting shoe (top-mounted)
- 40= Post (40/40, 60/40, 80/80 · 90 = timber 90/90)
- 100= Base plate length (100 mm · also 80 / 130 mm)
- Posts
- 40/40 · 60/40 · 80/80 mm
- Timber posts
- 90/90 mm (MZ90)
- Slope angle
- 10° / 20° / 30° sloped base
- Variants
- centred or flush-edge (-sb)
Fence shoes
- 01
Mark out the desired post spacing and drill the single central hole.
- 02
Clean the drill hole and mounting surface thoroughly to remove dust.
- 03
Apply injection mortar in front of and behind the drill hole.
- 04
Set the mounting shoe [1] in place, align it using a circular spirit level, let the mortar cure, and then tighten the concrete screw [2] firmly.
- 05
On the fence post, screw in the upper post screw [3], place the post onto the shoe [1], screw in the lower post screw [3], plumb with a spirit level, and tighten.
- 06
Insert the weather-resistant end cap [4] into the top of the fence post.
These guides do not replace project-specific structural engineering. Anchor type and post spacing depend on local substrate conditions and building regulations – when in doubt, consult us or a structural engineer.